Data center

Energiepark Wilhelmshaven

East of Sengwarden, a data centre and – on a separate site – a battery storage system are planned. All figures are planning stages.

Non-binding visualisation of the planned first construction stage. Design: Bright & Green.

Key facts

Sengwarden, Wilhelmshaven
Location
approx. 14 hectares
Area
approx. 100 MW
IT load
approx. 250 MW
Battery storage
approx. €1.45bn
Investment
approx. 4 to 5 years
Construction time

Every figure here is a planning stage and may change as the process continues.

The project

Project description

East of Sengwarden, Bright & Green is planning the Energiepark Wilhelmshaven: a data centre and, on a site of its own, a battery storage system. Bright & Green develops, plans, procures, delivers and manages the project.

In early September 2026 the project was presented publicly at a digital press conference, with the Minister-President of Lower Saxony, Olaf Lies, in attendance.

The project is at an early stage and has not yet been approved. Every figure on this page is a planning stage and may change as the process continues.

WilhelmshavenLower Saxony · Germany
North SeaJadebusenBremenOldenburgBremerhavenWilhelmshaven20 km

53.5292° N · 8.1136° E

The site

Where the energy park is to be built

The city of Wilhelmshaven put the land out to tender on the concept rather than the price. What decided it was not the highest bid but the most convincing overall concept, and Bright & Green was awarded the site.

The project company for the energy park is to be registered in Wilhelmshaven, so that the tax base stays where the plant is.

The area outlined in red east of Sengwarden, around nine hectares: this land is intended for the planned data centre alone. No battery storage is planned here; it is to be built on a separate site.

What is to be built

  • approx. 100 MWIT load at the final stage

    Co-location for AI and HPC loads, planned to the requirements of Tier IV

    across three construction stages

  • approx. 250 MWBattery storage

    Grid-serving and black-start capable, on a site of its own

    across two construction stages

Planning stage. The final design follows from the approval process.

Data centre and storage

Two plants, planned in stages

The data centre is planned as a co-location site, designed for AI and HPC loads and for the security requirements of Tier IV. It is to be built in three stages towards a target capacity of around 100 megawatts.

Beside it, a stand-alone battery storage system with a planned capacity of around 250 megawatts is intended – grid-serving and black-start capable, in two stages and on a site of its own. It is not to be built on the data centre's land.

Capital, time and work

approx. €1.45bnInvestmentacross a construction time of four to five years
  • Jobs in operationaround 550 to 600
  • During constructionaround 4,000

    short-term positions

Investment and timetable

Around €1.45 billion across four to five years

The planned investment comes to around €1.45 billion. Completion is currently expected to take about four to five years.

Operation is planned to be climate-neutral; hydrogen-ready gas turbines are to secure the power supply in emergency operation.

Running the park is expected to create around 550 to 600 jobs, and construction around 4,000 short-term positions.

François van Burk
Contact

Who to speak to about this project

For information on this project – planning, timetable and working together on the ground – François van Burk answers directly.

François van BurkCEO (Chief Executive Officer) · Bright & Green

Head office: +31 (0) 26 7620 883 · office@brightandgreen.de