Under construction

BESS-005 GBB Großbreitenbach / Thuringia

A stand-alone battery storage plant designed for four-hour operation is currently being built in Großbreitenbach (Thuringia). The DC side was successfully completed at the end of 2025. Commissioning is expected in the first quarter of 2027.

Project data

Location
Großbreitenbach, Thuringia
Plant rating
2,000 kW / 10,030 kWh
DC completion
2025 (for IAB 2023, 2024, 2025)
AC completion
February 2027
Commissioning
Q1 2027
Operating mode
AC-coupled / four-hour operation
Hardware
Container storage / string hybrid inverters (PCS)
Marketing
Grey power / flexibility marketing
Investment
from €93,000net
Storage share
from 208.96 kWh
Suitable for
IAB 2023

Only 6 storage packages left

As at September 2026

Request the investment documents

Your investmentStep 1 of 3

Investment volume€93,000 net

Have you already claimed the IAB (investment deduction)?
Yes
No

Not binding. You receive the documents on revenue streams, operating costs and term.

Battery storage in containers. The picture shows a completed plant, not the Großbreitenbach site.
The project

Project description

On a 3,000 m² commercial site in Großbreitenbach (Thuringia), a stand-alone battery storage plant designed for four-hour operation is currently being built. The direct-current side (DC) was completed at the end of 2025, and every component required has been ordered. Still to come are the work on the alternating-current side (AC) and commissioning, which is currently scheduled for the first quarter of 2027, expected at the end of March.

The plant has a grid connection capacity of 2,000 kW for both drawing and feeding in power. The installed storage capacity is 10,030 kWh. Four-hour operation as planned requires about 8,000 kWh; the remaining 2,000 kWh serve as a buffer to offset the expected degradation of the battery cells.

High-quality electrical components from German manufacturers are used. A warranty of up to ten years is intended for the main electrical components and the battery storage. Under the applicable policy conditions, liability insurance covers a loss of revenue of up to three months per insurance year.

On the basis of the current revenue forecast, a gross return in the double-digit percentage range is expected. The plant could be of particular interest for an IAB investment for the year 2023, since DC completion has already taken place and revenue is expected to follow soon.

Status

Schedule

The DC side is complete and every component required has been ordered. The work on the AC side and commissioning follow.

Where the project stands

  1. Equipment orderedCompleted
  2. DC completionEnd of 2025
  3. AC completionapprox. February 2027
  4. Commissioningapprox. Q1 2027
  5. Planned COD (marketing)approx. March–April 2027
The storage package

What a storage package comprises

The storage capacity is divided into 48 storage packages of equal size that can be bought individually. A storage package is a defined part of the plant that belongs to you and is accounted for separately.

Planning, procurement and construction lie with Bright & Green, as do operation, maintenance and marketing. Revenue streams, operating costs and term are set out in the documents you receive on request.