BESS-005 GBB Großbreitenbach / Thuringia
A stand-alone battery storage plant designed for four-hour operation is currently being built in Großbreitenbach (Thuringia). The DC side was successfully completed at the end of 2025. Commissioning is expected in the first quarter of 2027.
Project data
- Location
- Großbreitenbach, Thuringia
- Plant rating
- 2,000 kW / 10,030 kWh
- DC completion
- 2025 (for IAB 2023, 2024, 2025)
- AC completion
- February 2027
- Commissioning
- Q1 2027
- Operating mode
- AC-coupled / four-hour operation
- Hardware
- Container storage / string hybrid inverters (PCS)
- Marketing
- Grey power / flexibility marketing
- Investment
- from €93,000net
- Storage share
- from 208.96 kWh
- Suitable for
- IAB 2023
Only 6 storage packages left
As at September 2026
Project description
On a 3,000 m² commercial site in Großbreitenbach (Thuringia), a stand-alone battery storage plant designed for four-hour operation is currently being built. The direct-current side (DC) was completed at the end of 2025, and every component required has been ordered. Still to come are the work on the alternating-current side (AC) and commissioning, which is currently scheduled for the first quarter of 2027, expected at the end of March.
The plant has a grid connection capacity of 2,000 kW for both drawing and feeding in power. The installed storage capacity is 10,030 kWh. Four-hour operation as planned requires about 8,000 kWh; the remaining 2,000 kWh serve as a buffer to offset the expected degradation of the battery cells.
High-quality electrical components from German manufacturers are used. A warranty of up to ten years is intended for the main electrical components and the battery storage. Under the applicable policy conditions, liability insurance covers a loss of revenue of up to three months per insurance year.
On the basis of the current revenue forecast, a gross return in the double-digit percentage range is expected. The plant could be of particular interest for an IAB investment for the year 2023, since DC completion has already taken place and revenue is expected to follow soon.
Schedule
The DC side is complete and every component required has been ordered. The work on the AC side and commissioning follow.
Where the project stands
- Equipment orderedCompleted
- DC completionEnd of 2025
- AC completionapprox. February 2027
- Commissioningapprox. Q1 2027
- Planned COD (marketing)approx. March–April 2027
What a storage package comprises
The storage capacity is divided into 48 storage packages of equal size that can be bought individually. A storage package is a defined part of the plant that belongs to you and is accounted for separately.
Planning, procurement and construction lie with Bright & Green, as do operation, maintenance and marketing. Revenue streams, operating costs and term are set out in the documents you receive on request.